At the corner of Stringtown Road and Frederick Road, the plans show a tall, one-story building with a stone base. Two of its three bays are clad in red vertical metal panels, and the middle bay is beige with four evenly spaced windows. Montgomery Planning's staff report says it is meant to reference "the form and materials of a traditional barn, while providing a clear civic presence along Stringtown Road."
That building is the Clarksburg Library. A needs assessment called for it back in 2001, and the Clarksburg Master Plan has long promised it. The library now has an address, an architect, approvals and a construction schedule. Its location is the bigger news for anyone who lives here. Town Center was designed around a library on its central green, and that library is now going to the edge of the historic district along Stringtown Road. The neighborhood's long-awaited grocery store is also landing just off Stringtown.
The building at 23200 Stringtown Road
The county's Department of General Services project page lists the library at 23200 Stringtown Road and names Grimm and Parker Architecture as architect. The project is in the design document phase, and the county held a community meeting on October 6, 2026.
Here's what the Planning staff report describes:
- About 20,906 gross square feet on one level. The staff report says a single story allows greater accessibility and simpler library operations.
- A public meeting room for library programs and community use, plus collections for children and adults and materials that support schoolwork from early childhood through high school.
- 38 spaces in a garage under the library, 12 in a surface lot behind it, and nine parallel spaces on the Clarksridge Road Extension.
- A tree-lined walkway and lawn connecting the main entrance to a secondary entrance, with the historic Day House on the other side.
The barn look came from the Historic Preservation Commission review. The commission held five preliminary consultations with the county in 2025 and early 2026 and sent the project to the next stage of review in February 2026. In a February staff memo, the design team says it studied bank barns, hay barns and dairy barns, along with libraries and civic buildings from Frederick, Maryland to the West Coast. The memo also explains the red: barn paint used to be tinted with iron oxide, which made it last longer and kept moss and algae from growing.
Why it's on Stringtown Road and not the Town Center green
For years, county master plans named Clarksburg Town Center as the library site. In 2015, Third Try LLC, one of the Town Center developers, dedicated a 1.1-acre site to the county for it, as Bethesda Today reported in August.
The plan changed after a 2023 County Council law. It requires the Department of General Services to study whether affordable housing can share a site with new public facilities. Bethesda Today reported that Council Vice President Marilyn Balcombe said the Clarksburg library was the first project to go through that review. The October 2024 feasibility study concluded that "co-locating housing at the Town Center site was not advisable." It recommended another site about a 13-minute walk away, and the county bought it.
The new site still includes housing in the long-term plan. According to the March 2026 County Council staff report, the county plans to build affordable housing there once the library design is final. That housing is outside the library project's scope. The Planning staff report calls the housing a Phase II to be submitted later.
Clarksridge Road is meant to make the walk short
The library project includes the planned Clarksridge Road Extension, which will run from Clarksburg Square Road to Stringtown Road, with six-foot sidewalks on both sides. It connects to the existing sidepath on Stringtown Road and to a new sidepath planned along Frederick Road. The February preservation memo describes one design change made with that walk in mind. A pedestrian entrance was added at the garage level, so people coming down Clarksridge Road from Town Center don't have to walk around the building to get in from Stringtown.
The library's new neighbors also give it a longer history than the Town Center site would have. The site sits in the Clarksburg Historic District along Frederick Road, and its main historic structure is the Day House, a contributing resource dating to about 1925. The same stretch of road includes the Clarksburg Methodist Episcopal Church, whose congregation organized in 1788 and whose Gothic Revival building dates to 1909. It also includes Hammer Hill, a Queen Anne house built around 1891 to 1900. Montgomery Planning's Places from the Past guide traces Clarksburg back to Dowden's Ordinary, a hotel and tavern Michael Dowden built around 1754.
There's no final plan yet for the Day House. The county budget says General Services and Montgomery County Public Libraries are looking at ways to include it in library programming, and the project already pays for some site work to connect it to the library. The Planning staff report says talks about rehabilitating the house are at an early stage, and any work will need a Historic Area Work Permit.
The schedule, step by step
| Milestone | Date | Status |
|---|---|---|
| Historic Preservation Commission approval | July 29, 2026 | Done |
| Planning Board mandatory referral approval | July 30, 2026 | Done |
| Community meeting | October 6, 2026 | Held |
| Construction start | Summer 2027, in the county's FY28 | Scheduled |
| Completion | Spring 2029 | Projected in March 2026 |
The total project cost is now $40.3 million. That's about $6.7 million more than the previous approved plan. The Council staff report attributes the increase to added site work and parking, the Clarksridge Road extension, Stringtown Road requirements from the Department of Transportation, and design changes requested by the preservation commission. Once the branch opens, the county projects about 14.2 full-time positions and roughly $1.9 million a year in operating costs.
What happens to the Town Center lawn
The county still owns the site it originally set aside for the library. It's Parcel K on Plat 25338, at the corner of Clarksburg Square Road and Public House Road. Bethesda Today reported that Elm Street Development asked the Planning Board on July 30 to reconsider the move. Elm Street also said that if the library goes ahead on Stringtown Road, it would like the parcel back "to try to work with the community to come up with something … that could be complementary to the other uses in Clarksburg Town Center."
Balcombe told Bethesda Today she was open to that idea:
"I would support the county reverting back to the original owner, only because it's part of the community and we're not going to program the site."
The decision belongs to the county's executive branch. As of that August 12 article, the executive branch had not said it would give up the parcel. General Services Deputy Director Greg Ossont told the outlet the site is "currently used as passive open space for the surrounding community." He added that the county remains open to other civic or community uses. For now, the lawn at Clarksburg Square and Public House is still open space.
The grocery store has an address too
Town Center's other long-promised anchor is also moving forward along Stringtown Road. The MoCo Show reported in May that Weis Markets paid $5 million in April 2026 for a 4.5-acre grocery site on St. Clair Road, just off Stringtown Road. The plan is a standalone store of about 56,000 square feet with gas pumps.
That price stands out against the history the outlet described. Elm Street bought the Town Center property in 2011 for $1 and spent more than a decade on redesigns and road improvements before signing a grocery anchor. After the Weis sale, Elm Street was expected to start several retail buildings and about 190 apartments, adding roughly 50,000 square feet of retail, some of it on the ground floors of the apartment buildings. Montgomery Planning's October 2026 Countywide Retail Market Assessment still lists Clarksburg Town Center as "In Development." It says the commercial area will have more than 100,000 square feet of retail, including the Weis store.
On a map, the grocery store, the library and the new sidewalks of Clarksridge Road all sit along Stringtown Road. Once they're built, a Town Center resident's errands will run along that corridor more than through the central green.
Until spring 2029
The county's budget document says the closest library to Clarksburg is the Germantown branch, which opened in 2007. It's at 19840 Century Boulevard in Germantown. The county's population projection gives a sense of who the new branch will serve. Montgomery Planning estimates Clarksburg will grow from 29,200 residents in 2020 to 38,000 by 2050. For the latest on the building itself, check the Clarksburg Library project page. It lists the project team and the current phase, and it will be the place to watch for a contractor and a groundbreaking date. If you want more on how this part of upcounty Montgomery is growing, our Clarksburg neighborhood guide and our look at new construction in Clarksburg go into more detail.
At Shari Arciaga, we watch projects like this one because they shape everyday life on a street long before a ribbon gets cut. If you have a question about the new library, the Weis site, or how Clarksridge Road will tie them together, reach out anytime. You can also download the Ultimate Moving to Maryland Guide to share with friends who are curious about Clarksburg.